After years of delays and hundreds of millions of dollars in cost overruns, a Montreal rail system planned, built and largely financed by Canada’s second-largest pension manager is finally rolling.

Article content

(Bloomberg) — After years of delays and hundreds of millions of dollars in cost overruns, a Montreal rail system planned, built and largely financed by Canada’s second-largest pension manager is finally rolling. 

Advertisement 2

Article content

How it performs will determine whether the project was an expensive experiment or the start of a whole new business line for the C$402 billion ($304 billion) investment firm.

Article content

Caisse de Depot et Placement du Quebec undertook the 67-kilometer (42-mile) Réseau Express Métropolitain project in 2015 to link Montreal-Trudeau International Airport and several suburbs to the center of Canada’s second-biggest city. The project ran into unforeseen obstacles, including the Covid pandemic and the discovery of 100-year-old explosives in a tunnel, which pushed the budget from C$5 billion to more than C$7 billion ($5 billion).

The first phase of the system, known as the REM, opened on Friday, connecting the southern suburb of Brossard to Montreal’s central station. A second phase in the western suburbs will start next year, and the airport station is expected to be ready by 2027. 

Article content

Advertisement 3

Article content

Despite the challenges the project faced, CDPQ Chief Executive Officer Charles Emond praised his firm’s ability to see it through and said the firm is considering similar undertakings around the world.

“The Caisse is one of the few players in the world capable of conceiving, designing, planning, realizing and financing a project like this,” Emond said in an interview. “Whether we can do it internationally? Absolutely, it’s in the cards.”

‘World-Class Expertise’ 

Even with the delays, the project came to fruition quickly and the financial backing of CDPQ ensured the project went ahead, while similar projects like the AirTrain to LaGuardia Airport in New York have died, Emond said. 

The governments of Canada and Quebec invested about C$3 billion, and the Caisse covers the rest, including overruns. The pension fund expects a return of 8% to 9% over a 30-year horizon. It says an update of the overall costs will be provided in the coming weeks, though its yield forecasts won’t change. 

Advertisement 4

Article content

Caisse is already in a bidding process for a proposed high-frequency train running from Toronto to Quebec City, which could become one of the largest transportation projects ever built in Canada. However, the financial structure of that project is likely to be different than the REM, Emond said. 

“The construction industry has evolved, and engineering firms don’t want to take the risk in the same way,” he said.

Macky Tall, who led CDPQ’s infrastructure group until left in 2020 for a role at Carlyle Group Inc., sees the private sector playing a larger role in public transit projects. 

“Partnerships involving private investors will be critical to meet all of the investments that are required, both in terms of the financial contribution, but also the private capital bringing world-class expertise, efficiency and execution,” Tall said.

Still, the real test is yet to come for the Caisse’s project. The pandemic-initiated trend of remote work reduced ridership on the Montreal transit network by about 15%, Emond acknowledged. Fewer people also plan to use the new REM than before, with a 7% drop from 2019 to 2022, according to Hisham Negm, a transportation researcher at McGill University. 

“To build the light rail, you need a big number of people using the network,” he said. “Is it the right choice, or would a bus rapid transit be enough?”

Article content

Comments

Postmedia is committed to maintaining a lively but civil forum for discussion and encourage all readers to share their views on our articles. Comments may take up to an hour for moderation before appearing on the site. We ask you to keep your comments relevant and respectful. We have enabled email notifications—you will now receive an email if you receive a reply to your comment, there is an update to a comment thread you follow or if a user you follow comments. Visit our Community Guidelines for more information and details on how to adjust your email settings.

Join the Conversation

Stay connected with us on social media platform for instant update click here to join our  Twitter, & Facebook

We are now on Telegram. Click here to join our channel (@TechiUpdate) and stay updated with the latest Technology headlines.

For all the latest Business News Click Here 

 For the latest news and updates, follow us on Google News

Read original article here

Denial of responsibility! NewsAzi is an automatic aggregator around the global media. All the content are available free on Internet. We have just arranged it in one platform for educational purpose only. In each content, the hyperlink to the primary source is specified. All trademarks belong to their rightful owners, all materials to their authors. If you are the owner of the content and do not want us to publish your materials on our website, please contact us by email – [email protected]. The content will be deleted within 24 hours.