Eskom’s R3bn Ankerlig power station investment to support Koeberg

Energy regulator Nersa has published an application by Eskom to amend its generations license for the 1 327 MW Ankerlig OCGT power station near Atlantis in the Western Cape, which is in line for a planned R3 billion expansion.

The additional 100 MW it hopes to have in operation by March 2024 will mainly provide back-up off-site generation capacity for the Koeberg nuclear power station at nearby Duinefontein.

This comes as its Acacia power station at Edgemead in Cape Town that was built for this purpose reaches the end of its design life. Acacia has three 57 MW gas-fired units and was commissioned in 1976.

Read: SA’s nuclear energy housekeeping costs – who will foot the bill?

OCGTs are designed to provide additional generation capacity for relatively short periods of peak demand, but Eskom has been using its own and those of independent power producers extensively at huge cost, in an effort to avoid load shedding.

Eskom says the additional three units at Ankerlig are mainly to ensure compliance with nuclear safety standards by providing an additional, off-site power supply for Koeberg.

Should Koeberg’s primary power supply fail, the off-site facility will ensure that the plant can still shut down safely.

When not required by Koeberg, the planned units will be available to support the national grid in case of emergency, according to the state-run power company.

The Koeberg nuclear power plant in Duinefontein, Cape Town. Image: AdobeStock

Eskom has already appointed a contractor and hopes to have construction completed in 30 months. The targeted date for commercial use of the new units is March 2024, but Nersa has been requested to amend the license from March 2023.

Ankerlig currently burns diesel at exorbitant cost and Eskom has embarked on a feasibility study to convert all its OCGTs to use gas instead.

This is expected to drive down cost. The application to Nersa to increase generation capacity at Ankerlig is however still on the basis of diesel as feeding stock. The new units will have a design life of 25 years.

The Ankerlig investment comes as Eskom is embarking on a project to extend the life of Koeberg by 20 years. It is about to switch off its second unit this month to replace its steam generator – a process planned to take about ten months.

Read:
Why nuclear should form part of our Just Energy transition
Renewables won’t cut it, says Nersa

This will deprive the grid of 900 MW of generation capacity which almost equates one stage of load shedding.

When the work on Koeberg’s second unit has been completed, the first unit will be subjected to the same process.

On January 5, Eskom’s total generation capacity during the evening peak was 28 272 MW while the total demand was 25 931 MW. It did not use any OCGTs.

Stay connected with us on social media platform for instant update click here to join our  Twitter, & Facebook

We are now on Telegram. Click here to join our channel (@TechiUpdate) and stay updated with the latest Technology headlines.

For all the latest Business News Click Here 

 For the latest news and updates, follow us on Google News

Read original article here

Denial of responsibility! NewsAzi is an automatic aggregator around the global media. All the content are available free on Internet. We have just arranged it in one platform for educational purpose only. In each content, the hyperlink to the primary source is specified. All trademarks belong to their rightful owners, all materials to their authors. If you are the owner of the content and do not want us to publish your materials on our website, please contact us by email – [email protected]. The content will be deleted within 24 hours.